Program and Portfolio Management: Structure, Governance, and Oversight
CISA · Information Systems Acquisition, Development and Implementation · Bởi Super Admin
Understand how programs and project portfolios are structured, governed, and managed to support business objectives in the CISA exam context.
Understanding Programs and Their Structure
A program is an organization of many large, complex activities and can be thought of as a set of projects that work to fulfill one or more key business objectives or goals. A program is generally a multiyear effort that consists of many complex projects, each with its own project manager, project schedule, budget, and participants. This distinction is important for CISA candidates because programs represent a higher level of organizational commitment than individual projects and require a distinct governance approach.
A program is usually run by a program manager who has oversight over all the projects in the program. Like a single project, a program has a defined scope, budget, resources, and a schedule. Program management also helps to organize and coordinate the operation of its projects, identify dependencies between them, manage conflicts and issues, and manage common and shared resources used by project teams.
Figure: A circular diagram depicts a program hierarchy with a program manager at the center, overseeing multiple project managers. Each project manager leads a respective project team, illustrating the structured relationships within the program.
A program manager oversees several projects.
The image above illustrates the relationship between a program manager at the center and the multiple project managers and their respective project teams that the program manager oversees.
Starting a Program: Charters and Resources
When an organization sets objectives and goals that will be realized through a program, a number of activities usually take place. The first is the development of a program charter, which is a formal document that defines the objectives of a program, its main timelines, the sources of funding, the names of its principal leaders and managers, and the names of the business executive or executives who are sponsoring the program. The charter provides the formal authorization and direction needed to begin the program.
The second key activity is the identification of available resources. Senior management must identify the resources that will be used by the program, which include funding, personnel, and business assets such as information systems and other equipment. Together, the charter and resources provide the direction and the means to begin a program that will move the business closer to realizing its objectives. Without both elements in place, a program lacks either the formal mandate or the practical means to proceed.
It is also worth noting that many middle and senior managers function as program managers even if they do not have "program manager" in their title or job description. Any manager who is responsible for the execution of multiple concurrent projects, particularly if those projects are helping the organization get closer to common objectives, is functioning as a program manager in practice.
Running a Program: Key Management Activities
After a program has been launched, the program manager needs to manage it actively to ensure that the program is on track and fulfilling its objectives. This includes monitoring project schedules, which requires the program manager to examine each project's schedule periodically and communicate frequently with program participants and project managers to get up-to-date statuses on project tasks. It also includes managing project budgets, where the program manager monitors spending by each project and may need to make spending adjustments periodically to keep the overall program budget under control.
Additional responsibilities include managing resources across all projects and making changes as needed, since resources are scarce in most IT organizations and often require creativity to secure. The program manager must also identify and manage conflicts, as individual projects will often encounter resource conflicts — sometimes projects will vie for the same resources, or they may require resources in use outside of the program. Finally, the program manager is responsible for creating program status reports for senior management, which describe issues and conflicts and how they are being resolved, and sometimes describe unresolved conflicts that require senior management intervention in the form of resource prioritization.
Project Portfolio Management
The project portfolio is the organization's entire set of active projects at any given time. Unlike a program, where projects are related and support a common objective, a portfolio of projects is simply all the active projects, which may support many different and even unrelated objectives and be part of different programs. An organization needs to maintain a collection of information about all its projects in a central location so that senior managers or executives can quickly view high-level information about all active projects.
Information maintained in the project portfolio typically includes the executive sponsor, program manager, project manager, start and end dates, key milestones, names of participants, objectives or goals that the project supports, budget, resources used, and dependencies. This information is often stored electronically in a form that enables an executive to sort and filter company projects in various ways. Ease of access to project and program portfolios helps management better understand what activities are taking place and the resources that each is consuming.
Key takeaways
- A program is a multiyear effort consisting of many complex projects, each with its own project manager, schedule, budget, and participants.
- A program charter is a formal document defining objectives, timelines, funding sources, principal leaders, and executive sponsors.
- The project portfolio is the organization's entire set of active projects, which may support many different and unrelated objectives.
- Program managers must monitor schedules, manage budgets, manage resources, resolve conflicts, and report status to senior management.